What must happen
A nuclear power plant that is scheduled to start operation in 2013-2014 and run for decades must be built in accordance with the best available safety standards. Using a design and technology that are already almost 40 years old by definition fails to deliver a comfortable level of nuclear security, particularly after the Fukushima nuclear disaster. The need for this additional energy producing capacity should be critically reviewed and assessed. Before turning to the nuclear energy option, which carries a high-risk long-term potential for causing serious health hazards and environmental disasters, the Slovak government should look for the opportunities in improving energy efficiency and increasing renewable energy generation capacity.
Sectors | Nuclear Electric Power Generation |
Location |
|
The building of Slovakia's Mochovce 3 and 4 nuclear reactors is the longest running nuclear construction project
anywhere in Europe. The reactors were designed
by the Soviet Union back in the 1970s. Construction
began back in 1987 but in 1992, soon
after the collapse of the communist regime, it was suspended. Economic studies
in 2000 showed the project to be a financial disaster.
Although operating since the mid 1980s in
the Czech Republic,
Slovakia and Hungary, four of the same model of reactor as Mochovce
3 and 4 under construction in East
Germany, were cancelled in 1990 after the
German re-unification because the reactors did not meet basic safety standards.
Russia is
the only supplier of nuclear fuel for this type of reactor which makes a
mockery of the idea that nuclear power provides energy security. An estimated 22 tonnes of
spent nuclear fuel is generated by each reactor every year.
The investment
required to build Mochovce 3 and 4 is expected to reach 2.775 billion euros. This
will devour a massive 77% of SE's investment for new electricity generation
2007 to 2013. Due to the high financial risks for
investors, the Slovak government provides generous state aid that is very likely
illegal under EU legislation.
Social and human rights impacts
Serious concerns have been raised about the legitimacy of Mochovce 3 and 4's approval, safety issues and poor economics. The project is supposed to be finished on the basis of a permit issued by communist decision makers in 1986.
Since contamination ensuing from any accident would affect neighbouring countries, the people of Hungary and Austria are included in any public consultation. Questions asked at public forums held in Bratislava and Vienna remained unanswered. However, these meetings have revealed that the problem of final storage of high-level radioactive waste remains unsolved, while the commissioning of storage facilities for low and medium-level radioactive waste is being constantly postponed.
No attention for gender effects in EIA
The effects of radiation on vulnerable groups, especially pregnant women and small children, was not taken into account in the Environmental Impact Assessment. Radiation effects were only indicated in general terms.
Environmental and climate impacts
Low Nuclear Safety
Units 3 & 4 of Mochovce, by virtue of
their design which dates back to the 1970s, qualify among the most
outdated NPP projects in Europe at present. The outdated Soviet
technologies on which it relies are missing crucial safety systems
according to modern standards. The advanced stage of construction
allows only limited modifications and improvements ('retrofitting') to
the nuclear safety of the plant.
While current reactor designs
feature double containment structures (robust walls of concrete and
steel against leakage of radioactivity in case of heavy accidents, and
for protection of the reactor against external events such as an
airplane crash), Mochovce 3&4 has none. In addition, vulnerability
to seismic activity is a weakness in the safety design of VVER 440/213
units. It is not clear whether Mochovce 3 and 4 complies with the
latest seismic design standards of the International Atomic Energy
Agency (IAEA).
Preventing climate protection
Slovakia is a classical example where nuclear power is preventing the development of clean renewable energy solutions and is a barrier to energy efficiency measures. The amount of nuclear generated base-load in the Slovak electricity grid is so high, that proposed investments in wind energy projects by the utility ENEL had to be canceled.
Because of the need to sell the overload of capacity from its nuclear power stations, Slovakia has only marginally invested in energy efficiency measures in the electricity sector.
Other impacts
Nuclear risk export
In a plebiscite in 1987 Italy decided to close down all of its nuclear reactors due to safety concerns. This decision was confirmed after a referendum on nuclear in June 2011 when 90% of Italians said no to nuclear energy. As the Italian government has a 30% stake in ENEL, the utility company's engagement with the Mochovce 3&4 project is a clear example of nuclear risk export.
In 1993 the EBRD was approached by the Slovak government to help with the financing of units 1 and 2. EBRD commenced a comprehensive environmental assessment and least-cost study process. However, in 1995 the Slovak government decided to discontinue negotiations with the EBRD, citing as reasons the high cost of the loan and the condition imposed by EBRD to close down Slovakia's other NPP, Bohunice.
In October 2007 ENEL/Slovenské elektrárne (SE) announced the conclusion of a record corporate 7-year credit facility, totalling Euro 800 million from a consortium of international private banks, including ING, Calyon, Mizuho, Intesa San Paolo and KBC/CSOB (Mandated Lead Arrangers), Slovenská sporitelna (Lead Arranger), Komercní banka Praha, Komercná banka Bratislava and Dexia (Junior Arrangers).
85% of SE's investment portfolio exists of the Mochovce 3,4 nuclear power plant. The remaining 15% is smaller than 800 Million Euro. It is therefore clear that this corporate loan was at least partly meant for financing this project.
In January 2008, NGO campaigning scored an important success: the Dutch bank ING decided to withdraw from financing the commissioning of Mochovce NPP units 3 & 4, and to invest only in SE's other activities, such as energy efficiency improvement measures.
In April 2008 Erste bank followed suit by officially distancing itself from Mochovce NPP. The new agreement reached with SE is that the loan provided by the consortium of banks would not be used in any way for financing nuclear activities.
In november 2010, SE boasted in a public presentation that actually a "multi-purpose loan facility, secured by corporate cash flow, supplemented required funds" for the complemetion of Mochovce 3&4.
In March 2012, Bank Austria confirmed that it has closed down a financial facility to SE that could have been used for Mochovce 3&4.
Enel nuclear power plants
The ghosts of soviet nuclear - The case of Mochovce
Nuclear Fallout - Slovakia
2012
2012-03-13 00:00:00 | Bank Austria withdraws from Mochovce 3&4
In March 2012, Bank of Austria closed down a credit line to Slovenske Elektrarne that could have enabled the company to fund the buiding of Mochovce 3&4 by mutual agreement. This sends a clear signal to SE on the difficulty of funding such a dodgy deal.
2012-01-01 00:00:00 | Construction started but funding not sure
The constructions of Mochovce 3&4 started on the ground but it is still unclear if SE would need additional funding sources to be able to fund the completion of these new nuclear reactors.
2010
2010-05-01 00:00:00 | Final statement of approval on EIA
In May 2010, Slovenské Elektrárne, (SE) received the final statement of approval from the Environment Ministry for the Environmental Impact Assessment (EIA) for operation of the third and fourth units of the Mochovce nuclear power plant. This was the last step in the EIA process initiated at the end of 2008. The statement released by the Environment Ministry ends the EIA process and is one of the key documents necessary for the Nuclear Supervision Office (UJD) to issue a permit to launch the operation of the third and fourth units after their completion in 2012 and 2013.
2009
2009-07-01 00:00:00 | First EIA report
After heavy pressure from Greenpeace, Slovak NGOs, the Government of Austria and the European Commision, Slovak authorities decided in Summer 2008 that the Mochovce 3&4 project would need a full Environmental Impact Assessment. In early 2009, SE / ENEL started the EIA procedure. The first report was issued in July 2009, when a public participation period started. Public hearings were organised in Bratislava, Vienna (Austria) and Ezstergom (Hungary).
2008
2008-11-03 00:00:00 | Official start of the construction
On 3 November 2008, Slovak Prime Minister Robert Fice officially started construction of the Mochvoce 3&4 power station. Because of the fact that there is no final construction permit as of today, this action rather served as PR exercise.
2008-08-25 00:00:00 | Tender for builders
On 25 August 2008 Slovak power firm Slovenske Elektrarne (SE) launched a tender to find a builder to finish blocks 3 and 4 of Mochovce NPP. The deadline for final bids is 8 December 2008; construction works on units 3&4 was expected to start on 1 April 2009 and finish by the end of June 2011 (Reuters, 25 August 2008), while it is still going on in 2012. The tender was won by a consortium with Czech / Russian nuclear engineer Skoda JS and Slovak VUJE.
2008-07-01 00:00:00 | Conditioned opinion from European Commission
In July 2008, the European Commission issued a conditioned opinion on Slovakia's application to build new reactors at Mochovce, provoking indignant reactions from European Parliament MPs and Greenpeace. The opinion recommends, but does not oblige, the project proponent to ensure "an equivalent level of protection as a full containment" and to perform a thorough analysis of the measures needed in an aircraft crash scenario.